Question: View Policies Current Attempt in Progress Coronado Industries prepared a fixed buciget of 60000 direct labor hours, with estimated overhead costs of $300000 for variable

 View Policies Current Attempt in Progress Coronado Industries prepared a fixed

View Policies Current Attempt in Progress Coronado Industries prepared a fixed buciget of 60000 direct labor hours, with estimated overhead costs of $300000 for variable overhead and $90000 for fixed overhead. Coronado then prepared a flexible budget at 52000 labor hours. How much is total overhead costs at this level of activity? $260000 $338000 $390000 $350000 Save for Later Attempts:0 of 1 used Submit