Question: View Policies Current Attempt in Progress Pronghorn Company is constructing a building Construction began on February 1 and was completed on December 31. Expenditures were

 View Policies Current Attempt in Progress Pronghorn Company is constructing a

View Policies Current Attempt in Progress Pronghorn Company is constructing a building Construction began on February 1 and was completed on December 31. Expenditures were $ 1.920,000 on March 1, $ 1.200,000 on June 1, and $3,040,880 on December 31. Compute Pronghorn's weighted average accumulated expenditures for interest capitalization purposes. Weighted Average Accumulated Expenditures $ e Textbook and Media