Question: W 2 4 BUAD 3 0 6 Murphy Assignment 1 Project Management DO NOT SUBMIT THIS PAGE Task ID Task Duration ( Days ) Crash

W24 BUAD306 Murphy Assignment 1 Project Management
DO NOT SUBMIT THIS PAGE
Task ID Task
Duration
(Days)
Crash
Cost 1
Crash
Cost 2
A Sign lease for new kitchen 3
B Order/receive boxes/moving supplies 5 $1800 $1800
C Upgrade electric 4 $2000
D Get electric inspected 3
E Install new stove 3 $300
F Install new walk-in refrigerator 8 $800 $1200
G Get inspected 2
H Get Certificate of Occupancy 4 $2500
I Pack old kitchen 8 $150 $200
J Load Moving Vans/Move 2
K Unpack in new location 2 $2000
L Begin food preparation in new location ------
B C I J K L
A E
D G H
F
W24 BUAD306 Murphy LAST NAME FIRST:
Assignment 1 Project Management (25 pts) Due: Tues, 1/9/24 at 11:59pm EST via Canvas upload
Instructions: Print this page or complete via computer. Regardless, you must note answers in the box provided ONLY.
All supporting math must be shown in the corresponding space. Note: You must write neatly. If I cannot read it, you will
receive zero points.
When completed: Take a photo of this page/save file and SUBMIT ONLY THIS PAGE by the due date via the
corresponding Assignment link in Canvas. You must upload in a required format. NO HEIC files are permitted. NO LATE
SUBMISSIONS ARE PERMITTED.
1. Determine the paths for completion of this project, their durations, and the critical path. (5 pts)
Paths show letters for tasks Durations show individual #s
Total Duration (* next
to Critical Path)
2. If GETTING THE ELECTRIC INSPECTED (Task D) is delayed by 3 days, what is the resulting impact to the project (if
any) and why this happened (there is one very specific reason).(2 pts)
Answer: The resulting impact is:
Reason: This is because:
3. Assume the delay is eliminated (and you are back to the original results from Q1). If Wes and Steve want to
shorten the project by 3 days and have a budget of $3,000 to do so, will it be possible? You must show activities
crashed, total crash cost and proof using a crash diagram as taught in class lectures. (18 pts)
Paths (from above)
Total Path
Duration
(from above)
Crash Day 1
Task(s):
Crash Day 2
Task(s):
Crash Day 3
Task(s):
COST:
Total Cost $:
Is it possible to shorten
the project by 3 days for
$3,000 or less? Circle one:
Yes No
NOTE: Answer must be supported by
work to the leftW24 BUAD306 Murphy Assignment 1 Project Management
DO NOT SUBMIT THIS PAGE
Task ID Task
Duration
(Days)
Crash
Cost 1
Crash
Cost 2
A Sign lease for new kitchen 3
B Order/receive boxes/moving supplies 5 $1800 $1800
C Upgrade electric 4 $2000
D Get electric inspected 3
E Install new stove 3 $300
F Install new walk-in refrigerator 8 $800 $1200
G Get inspected 2
H Get Certificate of Occupancy 4 $2500
I Pack old kitchen 8 $150 $200
J Load Moving Vans/Move 2
K Unpack in new location 2 $2000
L Begin food preparation in new location ------
B C I J K L
A E
D G H
F
W24 BUAD306 Murphy LAST NAME FIRST:
Assignment 1 Project Management (25 pts) Due: Tues, 1/9/24 at 11:59pm EST via Canvas upload
Instructions: Print this page or complete via computer. Regardless, you must note answers in the box provided ONLY.
All supporting math must be shown in the corresponding space. Note: You must write neatly. If I cannot read it, you will
receive zero points.
When completed: Take a photo of this page/save file and SUBMIT ONLY THIS PAGE by the due date via the
corresponding Assignment link in Canvas. You must upload in a required format. NO HEIC files are permitted. NO LATE
SUBMISSIONS ARE PERMITTED.
1. Determine the paths for completion of this project, their durations, and the critical path. (5 pts)
Paths show letters for tasks Durations show individual #s
Total Duration (* next
to Critical Path)
2. If GETTING THE ELECTRIC INSPECTED (Task D) is delayed by 3 days, what is the resulting impact to the project (if
any) and why this happened (there is one very specific reason).(2 pts)
Answer: The resulting impact is:
Reason: This is because:
3. Assume the delay is eliminated (and you are back to the original results from Q1). If Wes and Steve want to
shorten the project by 3 days and have a budget of $3,000 to do so, will it be possible? You must show activities
crashed, total crash cost and proof using a crash diagram as taught in class lectures. (18 pts)
Paths (from above)
Total Path
Duration
(from above)
Crash Day 1
Task(s):
Crash Day 2
Task(s):
Crash Day 3
Task(s):
COST:
Total Cost $:
Is it possible to shorten
the project by 3 days for
$3,000 or less? Circle one:
Yes No
NOTE: Answer must be supported by
work to the left

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!