Question: Wagons are assembled in a process With two resources. A worker in the first resource assembles 0.35 wagons per hour and a worker in the

Wagons are assembled in a process With two resources. A worker in the first resource assembles 0.35 wagons per hour and a worker in the second resource assembles 1.6 wagons per hour. The first resource has 10 workers and the second resource has 5 workers. What is the capacity of this process in therms of wagons per hour? _____wagons per hour ROUND YOUR ANSWER TO TWO DECIMAL PLACES