Question: Wagons are assembled in a process with two resources. The first resource has a capacity of 2.7 wagons per hour. The capacity of the second

 Wagons are assembled in a process with two resources. The first

Wagons are assembled in a process with two resources. The first resource has a capacity of 2.7 wagons per hour. The capacity of the second resource is 2.3 wagons per hour. The first resource has 1 worker and the second resource has 7 workers. One additional worker is hired who is as productive as the current workers. Instruction: Round your answer to three decimal places. What is the new capacity of this process? wagons per hour