Question: Wally s Widget Warehouse takes orders from 7 A . M . to 7 P . M . The manager wants to analyze the process
Wallys Widget Warehouse takes orders from AM to PM The manager wants to analyze the process and has provided the following process flow diagram. There are three steps required to ship a customer order. The first step is to take the order from a customer. The second step is to pick the order for the customer, and then they have to pack the order to ready it for shipping. The ordertaking step works at a maximum rate of customer orders per hour. Order picking works at a maximum of per hour, and packing works at per hour.
Wally wants to figure out the following.
a What is the current maximum daily output of the process assuming that no one works overtime? ie meaning all three operations work a hour shift
b How long in hours will the picking and packing operations have to work to finish all the orders that were taken if we have a day where the order taker works at his maximum capacity? Round your answers to decimal place.
c Given b what is the maximum number of orders waiting to be picked?
d Given b what is the maximum number of orders waiting to be packed? Round your intermediate calculations to decimal place.
Management is considering doubling the packing capacity from to orders per hour Please answer the following based on that change.
e How long will the picking and packing operations have to work if we have a day where the order taker works at his maximum capacity? Round your intermediate calculations and final answers to decimal place.
f Given e what is the maximum number of orders waiting to be picked?
g Given e what is the maximum number of orders waiting to be packed?Wally's Widget Warehouse takes orders from AM to PM The manager wants to analyze the process and has provided the
following process flow diagram. There are three steps required to ship a customer order. The first step is to take the order from a
customer. The second step is to pick the order for the customer, and then they have to pack the order to ready it for shipping. The
ordertaking step works at a maximum rate of customer orders per hour. Order picking works at a maximum of per hour, and
packing works at per hour.
Wally wants to figure out the following.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock