Watch this video to learn how to successfully use Microsoft Project and answer the questions to check your knowledge on what you've learned. You can download the accompanying file to practice the process shown in the video if you have Microsoft Project installed on your computer. Note: You do NOT need access to the software to answer the questions.
The activities for the work packages are
a the deliverables for the project.
b a set of interrelated tasks that are dependent upon on another.
c unrelated tasks that are performed independently.
d the higher level in the hierarchical structure.