Question: WBS Activity Project Manager Project Engineer Contract Officer Data Manager Logistics Manager 1.3 Prepare RFP 1.3.1 Acquisition Plan R I C I C 1.3.2 Statement
| WBS | Activity | Project Manager | Project Engineer | Contract Officer | Data Manager | Logistics Manager |
| 1.3 | Prepare RFP | |||||
| 1.3.1 | Acquisition Plan | R | I | C | I | C |
| 1.3.2 | Statement of Work | R | C | C | C | C |
| 1.3.3 | Specification | A | R | I | I | C |
| 1.3.4 | Special Provisions | A | I | R | C | I |
| 1.3.5 | Data Requirements | A | C | C | R | C |
RACI Key. (R) Responsible, (A) Approve, (C) Consult, (I) Inform Figure 8-1 RACI Chart Consider the RACI chart presented in Figure 8-1 (RACI stands for Responsible, Accountable, Consult, Inform). Who is responsible for development of the specification?
| |||
| |||
| |||
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts