Question: WBS Code Activity Name Predecessor(s) Duration (hours) Explanation on duration 1 Charter signed off 1 To read and sign charter 2 Purchase supplies 3 Estimate

WBS Code

Activity Name

Predecessor(s)

Duration (hours)

Explanation on duration

1

Charter signed off

1

To read and sign charter

2

Purchase supplies

3

Estimate of going to store(s) and buying supplies

3

Shutters

3.1

Repair shutters

2

2

Small repairs needed

3.2

Paint shutters

3.1

1

Not a big area to paint

3.3

Hang shutters

7.2

0.5

need to make sure in correct position

4

Porch

4.1

Repair porch

2

8

Days work

4.2

Paint porch

4.1

5

Decent area to paint

5

Floor

5.1

Repair floor

2

8

Days work

5.2

Sand floor

5.1

4

Needs patience to deliver quality

5.3

Refinish (paint) floor

5.2

6

Decent area to paint

6

Painting

6.1

Paint ceilings

5.2

8

Difficult area to paint

6.2

Paint doors

6.1

5

Few doors to paint

6.3

Paint interior walls

6.2

8

Days work

6.4

Paint exterior walls

4.2

8

Days work

7

Windows

7.1

Wash exterior windows

6.4

4

Few windows to clean

7.2

Wash interior windows

6.3

4

Few windows to clean

7.3

Hang curtains

6.2, 7.2

2

Wont take that long

8

Project Completion

For the above table, what is the COMPLETE Activity on Node (AoN) network diagram (including float, ES, EF, LS, LF)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!