Question: WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48,000 48,000 50,000 2.02 Engines 22,000 21,000 23,000 2.03 Avionics 80,000 60,000
| WBS Element | Planned Value (PV) | Earned Value (EV) | Actual Cost (AC) |
| 2.01 Airframe | 48,000 | 48,000 | 50,000 |
| 2.02 Engines | 22,000 | 21,000 | 23,000 |
| 2.03 Avionics | 80,000 | 60,000 | 45,000 |
| 2.04 Communications | 30,000 | 30,000 | 30,000 |
| 2.05 Tech. Manuals | 42,000 | 42,000 | 48,000 |
| 2.06 Spares | 40,000 | 35,000 | 42,000 |
| 2.07 Training | 80,000 | 80,000 | 86,000 |
| Project Total | 342,000 | 316,000 | 324,000 |