Question: WBS Element Values Variance Performance Index Planned Value ( PV ) Earned Value ( EV ) Actual Cost ( AC ) Schedule ( EV -

WBS Element Values Variance Performance Index
Planned Value (PV) Earned Value (EV) Actual Cost (AC) Schedule (EV-PV) Cost (EV-AC) Schedule (EV/PV) Cost (EV/AC)
1.0 Design Process $10,000.00 $7,000.00 $12,000.00 $(3,000.00) $(5,000.00) $0.70 $0.58
2.0 Gather Tools $5,000.00 $3,000.00 $4,000.00 $(2,000.00) $(1,000.00) $0.60 $0.75
3.0 Perform Risk Analysis $7,500.00 $7,500.00 $8,000.00 $- $(500.00) $1.00 $0.94
4.0 Design Dashboard $10,000.00 $3,400.00 $3,400.00 $(6,600.00) $- $0.34 $1.00
5.0 Test Dashboard $5,000.00 $6,000.00 $4,000.00 $1,000.00 $2,000.00 $1.20 $1.50
6.0 Evaluate Results $13,000.00 $10,000.00 $12,500.00 $(3,000.00) $(2,500.00) $0.77 $0.80
Totals $50,500.00 $36,900.00 $43,900.00 $(13,600.00) $(7,000.00) $0.73 $0.84
Watch the video on earned value analysis. Using the values in this template, interpret the variances and indices (In bold above). You might use a word document for your explanation.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!