Question: WD Task ID Task Description Duration Immediate Predecessor(s) . Setup temporary fencing 5 days B Bulldoze & level grassland 9 days A area Cut and

WD Task ID Task Description Duration Immediate

WD Task ID Task Description Duration Immediate Predecessor(s) . Setup temporary fencing 5 days B Bulldoze & level grassland 9 days A area Cut and remove trees 6 days A D Bulldoze & level treed area 1 days Assume E Spread & compact gravel 5 days B, D that the only one bulldozer has been rented for the project. How many days should the project take? 22 days 17 days 19 days 20 days 23 days