Question: We are almost done with several components of implementation when the customer requests a change to the project that would increase the project risks. Which

We are almost done with several components of implementation when the customer requests a change to the project that would increase the project risks.
Which of the following should you do before all the others?
* Analyze the impacts of the change with the team
* Change the risk management plan
* Include the risk on the register and update schedule and cost
* Talk to the customer about the impact of the change