Question: We are planning a project and analyzing the following information: There is 15 % probability that the cost of materials will be $9,000 less than

We are planning a project and analyzing the

We are planning a project and analyzing the following information: There is 15 % probability that the cost of materials will be $9,000 less than expected There is 20 % probability of a delay in the receipt of some parts, with a cost to the project of $9,000 There is a 15% probability of a design defect, causing $ 7,000 of rework There is a 45 % probability that the construction of some activities may be simpler than expected, saving $1,500 There is a 20% probability that two parts will not fit together when installed, costing an extra $1,000 Based on this information, what are the cost contingency reserves that we should use

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!