Question: We have 10 exams {E1, E2, E3, ..., E10} and the task is to assign a hall and a time slot for each exam. The

We have 10 exams {E1, E2, E3, ..., E10} and the task is to assign a hall and a time slot for each exam. The set of available time slots is T = {t1, t2, t3, t4} and the set of available halls is {A, B, C,}. However, to provide correct assignments for the exams, we need to satisfy the following constraints: The 1st exam should take place before the third exam The 10th exam occurs after the 9th and 4th exams. The 1st, 3rd, and 4th exams should take place in either Hall A or Hall C. The 7th, 8th, 9th, and 10th exams should be in either Hall A or Hall B. There are no two exams occur at the same place and time. . . Please note the following: . The time slots are ordered chronologically based on the slot number. For example, the time slot t3 comes after t2, and so on. The above exam scheduling system can be modeled and solved as a constraint satisfaction problem CSP and you are supposed to provide a suitable assignment for the exams. Your solution should assign a tuple composing of a time slot and a hall for each exam, e.g., E2 (t4, A) You have to do the following: 1. Complete the formulation of this problem as a CSP in terms of variables, domains, and constraints. Constraints should be expressed implicitly using mathematical or logical notation rather than with words. 2. Implement the solver application for the above problem using either backtracking or local search based on the hill climbing technique. We have 10 exams {E1, E2, E3, ..., E10} and the task is to assign a hall and a time slot for each exam. The set of available time slots is T = {t1, t2, t3, t4} and the set of available halls is {A, B, C,}. However, to provide correct assignments for the exams, we need to satisfy the following constraints: The 1st exam should take place before the third exam The 10th exam occurs after the 9th and 4th exams. The 1st, 3rd, and 4th exams should take place in either Hall A or Hall C. The 7th, 8th, 9th, and 10th exams should be in either Hall A or Hall B. There are no two exams occur at the same place and time. . . Please note the following: . The time slots are ordered chronologically based on the slot number. For example, the time slot t3 comes after t2, and so on. The above exam scheduling system can be modeled and solved as a constraint satisfaction problem CSP and you are supposed to provide a suitable assignment for the exams. Your solution should assign a tuple composing of a time slot and a hall for each exam, e.g., E2 (t4, A) You have to do the following: 1. Complete the formulation of this problem as a CSP in terms of variables, domains, and constraints. Constraints should be expressed implicitly using mathematical or logical notation rather than with words. 2. Implement the solver application for the above problem using either backtracking or local search based on the hill climbing technique
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts