Question: We have a process shown in the right figure. ( M 1 - M 4 are names for four machines. The numbers are activity times

We have a process shown in the right figure. (M1-M4 are names for four
machines. The numbers are activity times in minutes). Consider a schedule:
schedule a job on M1 every 8 minutes, starting at time 0; schedule a job on M2
every 4 minutes starting at time 0. Jobs finished on M1 go to M4; jobs finished
on M2 go to M3.
Question 3(1 point)
Find the WIP on each machine and complete the table.
Keep three decimals if required.
M1=
A WIP (units).
M2=
A WIP (units).
M3=
A WIP (units).
M4
A WIP (units).
Total =
A WIP (units).Consider the Chipotle example we discussed in the class. But this time, both Under the arrival schedule given in the previous question Week 2 Exercise -
Gantt Chart, calculate the following run-time parameters:
Demand Rate:
A unit(s)/hour.
Flow Rate:
A/ unit(s)/hour.
Actual Cycle Time:
A sec/unit.
WIP for M1:
A/ unit(s).
WIP for M2:
A/ unit(s).
WIP for Buffer:
A) unit(s).
WIP for M3:
A/ unit(s).
Total WIP:
A/ unit(s).
Flow Time:
A)sec(s). We have a process shown in the right figure. (M1-M4 are names for four
machines. The numbers are activity times in minutes). Consider a schedule:
schedule a job on M1 every 8 minutes, starting at time 0; schedule a job on M2
every 4 minutes starting at time 0. Jobs finished on M1 go to M4; jobs finished
on M2 go to M3.
Question 3(1 point)
Find the WIP on each machine and complete the table.
Keep three decimals if required.
M1=
A WIP (units).
M2=
M3=
M4
M4
Total =
A WIP (units).
A WIP (units).
A WIP (units). The flow time (average throughput time)=
[minutes].
(Hint: Every 8 minutes, 3 job come to the process (1 job to M1,2 jobs to M2). To
get the average TPT, you need to calculate the throughput time for each of the
three jobs and then do an average.) Keep two decimals.
A/
Question 5(1 point)
The flow rate under the given schedule is =
[units/hour].
A/
workers M1 and M2 need a longer time to finish their tasks (the activity times
change to 90 seconds and 60 seconds, respectively).
Question 1(1 point)
Calculate the following design parameters for this process:
Cycle time (CT) for Stage 1:
A sec? unit.
CT for Stage 2:
A sec / unit.
Bottleneck is in Stage:
A/
Process Designed CT:
A sec / unit.
Process Capacity:
A/ units / hour.
 We have a process shown in the right figure. (M1-M4 are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!