Question: We have a process shown in the right figure. ( M 1 - M 4 are names for four machines. The numbers are activity times
We have a process shown in the right figure. MM are names for four
machines. The numbers are activity times in minutes Consider a schedule:
schedule a job on M every minutes, starting at time ; schedule a job on M
every minutes starting at time Jobs finished on M go to M; jobs finished
on go to
Question point
Find the WIP on each machine and complete the table.
Keep three decimals if required.
M
A WIP units
M
A WIP units
M
A WIP units
M
A WIP units
Total
A WIP unitsConsider the Chipotle example we discussed in the class. But this time, both Under the arrival schedule given in the previous question Week Exercise
Gantt Chart, calculate the following runtime parameters:
Demand Rate:
A unitshour
Flow Rate:
A unitshour
Actual Cycle Time:
A secunit
WIP for M:
A units
WIP for M:
A units
WIP for Buffer:
A units
WIP for M:
A units
Total WIP:
A units
Flow Time:
A We have a process shown in the right figure. MM are names for four
machines. The numbers are activity times in minutes Consider a schedule:
schedule a job on M every minutes, starting at time ; schedule a job on M
every minutes starting at time Jobs finished on M go to M; jobs finished
on M go to M
Question point
Find the WIP on each machine and complete the table.
Keep three decimals if required.
A WIP units
M
M
Total
A WIP units
A WIP units
A WIP units The flow time average throughput time
minutes
Hint: Every minutes, job come to the process job to M jobs to M To
get the average TPT you need to calculate the throughput time for each of the
three jobs and then do an average. Keep two decimals.
A
Question point
The flow rate under the given schedule is
unitshour
A
workers M and M need a longer time to finish their tasks the activity times
change to seconds and seconds, respectively
Question point
Calculate the following design parameters for this process:
Cycle time CT for Stage :
A unit.
CT for Stage :
A sec unit.
Bottleneck is in Stage:
A
Process Designed CT:
A sec unit.
Process Capacity:
A units hour.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
