Question: We have a process wih 3 employees each ringing up customers at their cash registers (serve customer from beginning to end). Process times are employee
We have a process wih 3 employees each ringing up customers at their cash registers (serve customer from beginning to end). Process times are employee 1 = 25 seconds per customer, employee 2 = 33 seconds per customer and employee 3 = 50 seconds per customer. What is the process capacity?
| a. | 144 customers per hour | |
| b. | 108 customers per hour | |
| c. | 72 customers per hour | |
| d. | 56 customers per hour |