Question: We have a stamping machine that can process 8 0 0 pieces per hour. We are feeding it manually and I would like to install

We have a stamping machine that can process 800 pieces per hour. We are feeding it manually and I would like to install an automatic feeder so we can use this machine to feed more stations and use the employee for other duties. If the employee can feed 115 pieces per hour to this machine, what is the % utilization right now?