Question: We have two mutually exclusive projects A and B. Both require initial costs of $10,000 and last for 4 years. Project A has expected
We have two mutually exclusive projects A and B. Both require initial costs of $10,000 and last for 4 years. Project A has expected future cash flows of $4,000, $5,000, $8,000 and $3,000, respectively. Project B has expected future cash flows of $8,000, $9,000, $2,000 and -$3,000. If the required return for project A is 20% and the required return for project B is 9%, which project should we start? O Have no idea O Start both projects because both of them have positive NPVs O B. Because its npv 4333.66 is higher than the NPV of A, which is 2881.94. O A. Because its NPV is $5158.19 which is higher than the NPV of project B, which is $4333.66
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
