Question: We need to install a new cable network between the 1 0 nodes shown in Graph G below for the least total cost . The
We need to install a new cable network between the nodes shown in Graph below for the least total
cost The weighted graph shows the new cable's installation cost along each path.
i Find the minimum spanning tree for this graph G using Prim's Algorithm. Consider as starting vertex.
ii Calculate the Total cost.