Question: We plan to create 2 pages per week which will earn $ 2 , 0 0 0 / week . This is the planned value.

We plan to create 2 pages per week which will earn $2,000/week. This is the planned value.
At the end of the first week, only 1 page has been completed (earned value) and we have spent $1,500(actual cost). Are we ahead or behind schedule, over or under budget?
PV = $2,000
EV = $1,000(1 page = $1,000)
AC = $1,500
CV EV AC
SV EV PV
CPI EV/AC
SPI EV/PV