Question: We plan to create 2 pages per week which will earn $ 2 , 0 0 0 / week . This is the planned value.
We plan to create pages per week which will earn $week This is the planned value.
At the end of the first week, only page has been completed earned value and we have spent $actual cost Are we ahead or behind schedule, over or under budget?
PV $
EV $ page $
AC $
CV EV AC
SV EV PV
CPI EVAC
SPI EVPV
Step by Step Solution
There are 3 Steps involved in it