Question: We understand that PERT and CPM have been used to plan, schedule, and control a wide variety of projects. List the four projects according as

We understand that PERT and CPM have been used to plan, schedule, and control a wide variety of projects. List the four projects according as they appear on the text.
Construction of a new building
Development of a software application
Manufacturing of a new product
Planning a large-scale event
According to the text in use, explain briefly what is the difference between PERT and CPM?
The difference between PERT and CPM is that PERT is a probability model, and CPM is a deterministic model. PERT is used to manage uncertain activities of projects while CPM is used to manage only certain activities of any project.
We understand that PERT and CPM have been used to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!