Question: Week 1 2 3 4 5 6 Forecast 40 40 45 45 50 50 Orders 35 24 12 3 Available (10) ATP MPS (11 points)

Week

1

2

3

4

5

6

Forecast

40

40

45

45

50

50

Orders

35

24

12

3

Available (10)

ATP

MPS

  1. (11 points) Demand information for a product for the next six weeks is as shown. Production batch size is 80 units and there is a safety stock requirement of 8 units.

  1. Complete the master production schedule (use discrete ATP)

Week

1

2

3

4

5

6

Forecast

40

40

45

45

50

50

Orders

Available ()

ATP

MPS

  1. For each of the following new orders, show, by updating the MPS, whether the order can be accepted without the need for additional production (orders cumulate, use discrete ATP)

  1. Week 4, 40 units

Week

1

2

3

4

5

6

Forecast

40

40

45

45

50

50

Orders

Available ()

ATP

MPS

  1. Week 2, 30 units

Week

1

2

3

4

5

6

Forecast

40

40

45

45

50

50

Orders

Available ()

ATP

MPS

  1. Week 1, 10 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock