Question: week bag invent 1 2 3 4 5 6 7 8 gross requirements 100 0 100 200 100 200 200 100 schedule receipts 200 0
| week | bag invent | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| gross requirements | 100 | 0 | 100 | 200 | 100 | 200 | 200 | 100 | |
| schedule receipts | 200 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| projected on hand inventory | 200 | ||||||||
| planned receipts | |||||||||
| planned order releases | |||||||||
Identify the projected on hand inventory at the end of week 4 in the following MRP problem (use numbers only, do not type the word units)
Item:C Description: Pedestal Assembly Lot size: POQ=3weeks
Lead time: 2 weeks
Safety stock:60