Question: Week TBC 3 5 6 7 8 g 10 Task 310 10 L Task 2 70 10 10 10 20 10 10 Task 3 40

 Week TBC 3 5 6 7 8 g 10 Task 310

Week TBC 3 5 6 7 8 g 10 Task 310 10 L Task 2 70 10 10 10 20 10 10 Task 3 40 25 Task 4 30 5 70 Tota 170 10 25 15 10 25 15 35 20 Cumulative Amounts are in thousands of dollars. The cumulative budgeted cost at the end of week 6 is 100 (thousands of dollars). (10 + 25 + 15 + 10 + 25 + 15) 3b. Below is a table of actual costs. What is the cumulative actual cost at the end of week 6? Determine whether there is a cost overrun or under-run. What is causing it