Question: Weeks 2 - 4 Version A . Complete the bubble sheet for Qs 1 - 1 2 Total 1 2 marks - 1 % of

Weeks 2-4
Version A. Complete the bubble sheet for Qs 1-12
Total 12 marks -1% of grade
12 MCQ =12 marks
Time allowed: 25 minutes
1) Aproject is disinct from operations workin that it meets 5 critera. Which of the below is not one of the
criteria discussed in class:
A) The work has a clear outcome
B) There is a potential for risk
C) The work is assigned a project leader
D) The work has a defined beginning and end
E) The end result is unique
2) Deliberately adapting the approach of a project as it relates to governance so that it better suits the work being done is an example of:
A) Tailoring
B) Streamlining
C) Adaptive planning
D) Flying "by the seat of your pants"
E) Rogue leadership
3) The Guide to the Project Management Body of knowledge is descriptive, not prescriptive. In class, it was referred to as "a(n)
not a(n)
A) "stopwatch", "hourglass"
B) "cookbook", "recipe"
"exception",
"rule"
"rule", "exception"
E) "recipe", "cookbook"
Artifacts that are outputs of a project's initiation phase may include.
4) Project charters
3) Contracts
) Gantt Charts
) Statements of Work
A, B and D
ior leaders, other project managers, and line employees are project stakeholders. Which category of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!