Question: Well testing taking place before permanent well completion is referred to as drill stem testing. After a testing well drilled, a oil company has found
Well testing taking place before permanent well completion is referred to as drill stem testing. After a testing well drilled, a oil company has found that a permanent well will generate cash flow for $30 million per year for the next 5 years. The testing well costs $25 million to drill and the permanent well costs $100 million. The company's cost of capital is 15%. Should the company go ahead to drill a permanent well
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts