Question: What action does a Release Train Engineer take prior to an upcoming Program Increment (PI) Planning meeting? Ensure that at least 30% of the Program
What action does a Release Train Engineer take prior to an upcoming Program Increment (PI) Planning meeting?
- Ensure that at least 30% of the Program Backlog is allocated to Enabler Features
- Allocate time in the scrum of scrums meeting for Product Management to socialize with the teams the Features for the upcoming PI
- Provide approval and sign-off for draft Team Backlogs
- Facilitate Product Management and other stakeholders in prioritization of the Program Backlog