Question: What action would be taken during the effort reporting component of the kickoff meeting? A . ) Detailing how team members should alert the project
What action would be taken during the effort reporting component of the kickoff meeting?
A
Detailing how team members should alert the project managerwhen the hours needed to complete tasks go beyond the estimates
B
Deciding when project team meetings would occur and who would be involved
C
Preparing copies of the scope, governance, and schedule for team members to review
D
Creating a RACI to share with each team member