Question: What additional statistical analysis does PERT allow for beyond identifying the critical path? Group of answer choices Identifying the tasks that can be skipped without

What additional statistical analysis does PERT allow for beyond identifying the critical path?
Group of answer choices
Identifying the tasks that can be skipped without affecting the project schedule
Reducing the estimated times for all tasks by a uniform percentage
Calculating confidence intervals and probabilities of completion times
Calculating the exact cost of the project