Question: What are some possible solutions and which choice would you choose? How would you implement your plan? How would you track the progress of your

What are some possible solutions and which choice would you choose?

How would you implement your plan? How would you track the progress of your plans execution?

Avion Inc.

Susan Dey and Bill Mifflin, procurement managers at Avion, Inc., sat across from each other and reviewed a troubling performance report concerning a key supplier, Foster Technologies. The report detailed the deteriorating performance of Foster Technologies in the areas of material quality and on-time delivery.

Susan: I dont believe what I am seeing. This supplier was clearly a star when we performed our supplier visits before awarding the contract for the new Amrod product line.

Bill: Im not pleased. I was on the team that performed the audit and site visit. Fosters management was so smooththey indicated they could meet all our requirements. I feel like weve been misled by this supplier.

Susan: Didnt you look at their processes and quality systems?

Bill: Sure we did. Everything checked out fine. But now every other shipment has some problem, and the delays are hurting our ability to get our product to our customers. What really struck us about this supplier was how innovative they were. Fosters biggest drawback was their sizethey lacked some depth at key manufacturing engineering positions. Maybe thats why they are having problems. It could be that someone has left the company.

Susan: We are going to have to address these problems quickly.

Bill: Ill tell you what I am going to recommend. We should begin immediately to look for another supplier. I never was a fan of these single-source contracts. They leave us open to too much risk.

Susan: But wont that take a long time?

Bill: Sure. Well have to perform another supplier search with team visits. New tooling could really cost, too. This could take months.

Susan: Has anyone talked with the supplier about these problems?

Bill: Kevin went over personally today and talked with the production manager. He didnt have much time to explain, but he indicated on the phone that Fosters production manager said we should accept responsibility for a good part of the problems that are occurring!

Susan: Why should we? I think they are just trying to shift the blame for their poor performance.

At this point, Kevin ODonnell, another procurement manager, entered the room.

Bill: Kevin, glad youre here. We were just discussing how Foster is trying to blame us for their problems. I think we should dump them fast!

Kevin: Yeah, well, Ive got news for you two. I think Fosters production manager is correct. I think I would be frustrated with us, too!

Susan: What are you talking about?

Kevin: I spent a good part of the day over at Foster and learned some interesting things. For example, do either of you remember what we told Foster the monthly volume requirements for the product would be?

Bill: I remember exactly. The volumes were projected to be 2,500 units a month. So whats the problem?

Kevin: We need to talk with our production group more often. The monthly volumes are now over 4,000 units a month! And not only that, our production group now wants material within 10 days of a material release rather than two weeks. We have also been changing the final material release quantities right up to the last minute before delivery.

Bill: Uh oh. I remember on our site visit that the most their production system could handle was 3,500 units a month. And a two-week lead time was about as low as they could go.

Susan: But why didnt they inform us that these changes were causing problems? They still have some explaining to do.

Kevin: Apparently they tried. What did your team tell this supplier about communicating with us after you finished negotiating the contract?

Bill: We said that any operational problems or issues have to go through our materials management people. The team was responsible for evaluating and selecting the supplier and then negotiating the agreement.

Kevin: Fosters production manager produced a log detailing seven memos and letters outlining the impact of our production and scheduling changes on their operation. He also called us several times with no response. Each of these inquiries received little attention on the part of our materials group. Im not sure how fond Foster is of us as a customer. I think they are anxious for this contract to wind down so they can dump us!

Susan: What do we do now?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!