Question: What are the critical paths? What is the expected duration of the project? Which path has the lowest duration? What is the slack for the

What are the critical paths?
What is the expected duration of the project?
Which path has the lowest duration?
What is the slack for the path with lowest duration?
data. Note: Draw the network diagram in order to answer the following question correctly. Activities A, B and C are starting activities. TIP: place dummy activity 'x' right after activity B, and place dummy activity 'y' right after activity F. Activity Precedes Duration (days) A D B E 3 E F, G, H E F, G, H IF End End . EndStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
