Question: What are the incorrect statements regarding the disposition process for Class I (not Class II) Engineering Change Proposals (ECPs)? Disposition must be approved or disapproved
What are the incorrect statements regarding the disposition process for Class I (not Class II) Engineering Change Proposals (ECPs)?
- Disposition must be approved or disapproved for implementation by a properly constituted Government Configuration Control Board
- Unless otherwise specified in the contract, the government administrative contracting officer or plant representative serves as the disposition authority
- Government concurrence in normally allows the contractor to incorporate the change in applicable item and update its configuration documentation without anyfurther government action or authorization being required
- The default action is concurrence/non-concurrence in classification only, unless the contract requires approval/disapproval.