Question: What are the inputs to the plan cost management process? Select one or more: a. Project management plan b. Cost management plan c. Project charter

What are the inputs to the plan cost management process?

Select one or more:

a. Project management plan

b. Cost management plan

c. Project charter

d. Enterprise environmental factors

e. Organizational process assets

f. Expert judgment

Which elements are inputs to the control cost process?

Select one or more:

a. Project funding requirements

b. Project management plan

c. Change requests

d. Organizational process assets

e. Work performance data

f. Project documents

g. Cost forecasts