Question: What are the objective coefficients ranges for the three components? If required, round your answers to two decimal places. Variable Objective Coefficient Range C 1

What are the objective coefficients ranges for the three components? If required, round your answers to two decimal places.
Variable Objective Coefficient Range
C1
No Lower Limit
to
- Select your answer -
C2
5.33
to
- Select your answer -
C3
- Select your answer -
to
No Upper Limit
Interpret these ranges for company management.
Individual changes in the profit coefficients
within
these ranges will not cause a change in the optimal number of components to produce.
(c) What are the right-hand-side ranges?
Constraint Right-Hand-Side Range
1
- Select your answer -
to
- Select your answer -
2
- Select your answer -
to
No Upper Limit
Interpret these ranges for company management.
These are the ranges over which the shadow prices for the associated constraints
- Select your answer -
applicable.
(d) If more time could be made available on the grinder, how much would it be worth? Explain.
It would be worth nothing
, because the constraint related to the time available on the grinder
- Select your answer -
binding.
(e) If more units of component 3 can be sold by reducing the sales price by $4, should the company reduce the price?
No
, because the production of component 3 would be
less
profitable than the production of the other two components and at the reduced price
none
of component 3 would be produced.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!