Question: What are the scaffolding A . 3 , 3 , 3 , 3 , 3 manpower levels per week based on the following criteria:piping direct

What are the scaffolding
A.3,3,3,3,3
manpower levels per
week based on the
following criteria:piping
direct labor hours =3,750
five-week
durationutilizing 20% of
the piping hours for
scaffolding hoursworking
50 hours per week
Select one:
A.3,3,3,3,3
B.5,5,5,5,5
None of these answers
15,15,15,15,15