Question: What are the values for ES, EF, LS, LF for Activity G? What are the values for ES, EF, LS, LF for Activity H? What

What are the values for ES, EF, LS, LF forWhat are the values for ES, EF, LS, LF for

What are the values for ES, EF, LS, LF for Activity G?

What are the values for ES, EF, LS, LF for Activity H?

What is the critical path(s) and its duration?

What is the total cost using the duration found in the previous question?

What is the total cost after reaching 45 weeks?

What is the critical path(s) once the project reaches a duration of 45 weeks?

What is the maximum number of crashes for Activity G?

What is the crash cost per week for Activity B?

You have decided to provide your project management skills to aid the T4K effort as they plan a new route through the Appalachian Mountains, and you realize there are many activities that must take place at the same time. Step Activity A Route selection B Camping Site selection Plan submission to T4K D Plan approval Camp Site acquisition F Place riders on route G Ride route H Write thank you notes Predecessor(s) Duration (Weeks) None 8 None 11 None 3 16 B 12. A, B 14 E, F. 22 D G 3 Step Normal Time (Weeks) Crash Time ( Weeks) Normal Cost ($) Crash Cost ($) Crash Cost Per Week A 8 6 5000 7000 B 11 9 2500 8000 3 2 3000 6000 D 16 12 2000 12000 E 12 9 3000 10500 F 14 12 21000 25500 G 22 16 44000 62000 H 3 3 2400 n/a Start 1st Crash 2nd Crash 3rd Crash 4th Crash Bh Crash Bh Crash PATHS Minimum Project Duration Critical Path(s) Activities Crashed Incremental Cost Total Cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!