Question: What csn a project manager do to determine if workers are overloaded? A . Ask them if they are too busy B . Check to
What csn a project manager do to determine if workers are overloaded?
A Ask them if they are too busy
B Check to see if they have been working overtime
C Checkbthe network diagram for resource overloads
D Add the demands for each resource at each time period