Question: What data analysis technique determines whether the schedule is on track by measuring the results of each activity against the planned values in the schedule
What data analysis technique determines whether the schedule is on track by measuring the results of each activity against the planned values in the schedule baseline? Re-estimation of remaining components on project Trend Analysis Performance Reviews Schedule compression