Question: What decision authorizes entry into the Production and Deployment phase? Milestone A decision Milestone B decision Completion of a validated and approved Capability Development Document
What decision authorizes entry into the Production and Deployment phase?
Milestone A decision
Milestone decision
Completion of a validated and approved Capability Development Document CDD
Milestone decision