Question: What do we calculate when we subtract the Earliest Start time ( ES ) from the Latest Start time ( LS ) in a project
What do we calculate when we subtract the Earliest Start time ES from the Latest Start time LS in a project network?
Question options:
Earliest finish time
Project delay
Critical time
Activity Slack