Question: What documentation would a project manager use to determine the activity duration for an activity? Only using past projects as a guide Searching the Internet
What documentation would a project manager use to determine the activity duration for an activity? Only using past projects as a guide Searching the Internet project management Web sites for similar projects with similar objectives and resource needs Performing a PERT analysis Scheduling a meeting with functional managers to discuss the work and leave the decisions to them