Question: What does integration, coordination control of projects better ensure? Work can be independent of original project plan. Corrective actions are approved through the change control
What does integration, coordination control of projects better ensure?
Work can be independent of original project plan.
Corrective actions are approved through the change control process.
Changes during the monitoring and control phase do not need to be communicated to the team.
Root causes for variances are not taken into consideration.