Question: What does it mean to mitigate in response to a negative risk? a. To adopt less complicated processes to reduce the probability of risk b.
What does it mean to "mitigate" in response to a negative risk?
a. To adopt less complicated processes to reduce the probability of risk
b. To acknowledge the risk and not take action
c. To change the project plan to eliminate the threat
d. To shift the impact of a threat to a third party