Question: What does it mean when earned value is above planned value? : More was spent for the work completed than planned, and the project is
What does it mean when earned value is above planned value?
:
More was spent for the work completed than planned, and the project is behind schedule.
More work has been completed than planned, and the task or project is ahead of schedule.
Less was spent for the work completed than planned, and the project is under budget.
Less work has been completed than planned, and the task or project is ahead of schedule.