Question: What does sequencing activity entails? a . going through the network to ensure that no dead - ends are present b . replace an old
What does sequencing activity entails?
a
going through the network to ensure that no deadends are present
b
replace an old system where the new capability must be started before the old one is completely discontinued.
c
the logical order in which project activities can be accomplished
d
the activity that follows a predecessor activity, as determined by their logical relationship