Question: What does the buyer's project manager need to control in a Time and Materials (T&M) contract? Question 9 options: a) Total cost incurred by the
What does the buyer's project manager need to control in a Time and Materials (T&M) contract? Question 9 options: a) Total cost incurred by the seller b) Scope changes initiated by the seller c) Material costs only d) Seller's fixed fee