Question: What does the 'Critical Chain Method' in project management focus on ? Group of answer choices Enhancing team communication Aggregating safety time along the critical
What does the 'Critical Chain Method' in project management focus on
Group of answer choices
Enhancing team communication
Aggregating safety time along the critical path into project buffers
Decreasing overall project budget
Reducing the number of project tasks