Question: What happens if a task on the Critical Path is delayed? Group of answer choices The project cost increases. The entire project is delayed. Other
What happens if a task on the Critical Path is delayed?
Group of answer choices
The project cost increases.
The entire project is delayed.
Other tasks on the Critical Path can compensate for the delay.
Only that specific task is delayed.