Question: What happens if there is a delay in completing an activity on the critical path? a . It changes the sequence of activities on the
What happens if there is a delay in completing an activity on the critical path?
a It changes the sequence of activities on the critical path
b It has no impact on the project completion time
c It extends the project completion time
d It shortens the project completion time